Cummins: batteries can help AI data centers meet tightening grid rules on large loads

Cummins argues battery energy storage can act as a shock absorber for AI data centers whose power demand spikes faster than the grid can react — and that regulators are starting to require it.

Share of total load an AI data center can demand
80%
Data center load disconnected in the July Northe
More than 3 GW
Capacity of the Cummins BESS platform used in th
5 MWh
Uptime data center operators demand
99.9%

What Happened

AI workloads are pushing data centers to demand huge blocks of power, and regulators in key markets are tightening the rules that govern how those facilities connect to the grid. For decades, planning on-site power was mostly an economics exercise: operators calculated total cost of ownership, chased the lowest immediate energy costs and made their own decisions on how to balance their power needs. Now, as massive facilities demand ever larger loads, utilities and Independent Systems Operators are introducing mandates to protect aging grids. Cummins says battery electric storage systems (BESS) offer a pathway to being a good grid citizen under these new rules.

Regulatory frameworks tightening around large loads
  • United States: the Federal Energy Regulatory Commission (FERC) has mandated that regional transmission organizations (RTOs) modernize their tariffs for connecting data centers and other large energy users.
  • United States: the North American Electric Reliability Corporation (NERC) has enacted rigorous monitoring and compliance frameworks such as Level 3 Alerts and specialized task forces, reclassifying large data center loads as system-critical entities that must provide granular data on computational load profiles.
  • Ireland: new large load mandates take effect in the third quarter of 2027, requiring every data center to be able to power itself entirely from its own generation if needed and to pass system stability tests.
  • Taiwan: big power consumers are being required to install generation and energy storage facilities.
  • Australia: the Australian Energy Market Commission (AEMC) is finalising a mandate for data centres to meet specific disturbance ride-through requirements, staying connected during certain voltage and frequency disturbances and recovering power within defined timeframes.
“Until now, if the data center, for any reason, chose to cut off from the grid, the power supply would be reabsorbed by the utility and transferred somewhere else. But with so many big data centers coming on stream, it's putting strain on an infrastructure geared to the same level of operations it was handling 20 or 30 years ago. What utilities and ISOs are saying today is they will guarantee a certain level of support in terms of power needs but only if the data center behaves as a good grid citizen and commits to doing its duty.”
— Dinesh Balaji Ramaraj, Marketing and Business Development Manager for Cummins New Energy Solutions
The ramp-rate mismatch
Data center demand
150 megawatts within a single second
Grid delivery
20 megawatts per minute

Unlike traditional cloud workloads with steady, predictable demand, an AI data center can demand up to 80 percent of total load within a few milliseconds, and the grid simply cannot react that quickly. Forced to absorb or deliver power at such velocity, grids experience severe sagging, overshooting and frequency instability, so grid operators are capping how fast facilities can ramp up demand. Cummins says BESS acts as an immediate shock absorber, providing millisecond-level response to smooth rapid load changes and buffer short-duration spikes. In a resilient data center the batteries work with generators, switchgear, transformers and building management software: batteries handle the instant, high-frequency transients while diesel or natural gas generators provide long-duration backup for extended outages. Traditional emergency generators, Cummins notes, are mechanically unsuited to continuous millisecond-to-millisecond fluctuations.

Cummins' largest BESS deployment to date
  • Cummins is working on its largest BESS deployment so far — a multi-gigawatt hour data center campus project for a hyperscaler in the US.
  • The deployment uses Cummins' 5 MWh platform with lithium iron phosphate (LFP) battery chemistry and integrated liquid-cooling thermal management.
  • The system has a flexible modular architecture compatible with various power conversion and energy management systems.
  • The same platform is used in 'bridge-to-grid' solutions engineered to integrate with traditional generator sets and microgrid ecosystems.
  • Millisecond-level fast charging and discharging is designed to mitigate transient power spikes and support the 99.9% uptime data center operators demand.

Cummins stresses that energy storage should never be viewed as a standalone fix: Ramaraj says the true value of a BESS depends entirely on intelligent site modeling, accurate load profiling, advanced controls and holistic system design. Deployment success requires early focus on ramp rates, telemetry, utility coordination, operating modes, rigorous testing regimens and future compliance expectations. Teams should also engage at the earliest opportunity with utilities, ISOs, RTOs, consultants and technology partners. Handling these issues from day one reduces the risk of interconnection delays, costly redesigns and unexpected expansion constraints, and supports uptime, resilience and future growth.

Previously from Cummins Inc.

Cummins has previously explained why standby generators fail in outages and how maintenance prevents it, saying the generators must work instantly during an outage, so maintenance, fuel quality, environmental care and transfer-switch testing must be handled before the power fails.

Background drawn from MotorClaw's earlier coverage of Cummins Inc.'s official releases.

Why this matters

AI data centers are among the largest and least predictable power users on the grid, and regulators in the US, Ireland, Taiwan and Australia are tightening the rules for connecting them. That pushes operators toward on-site batteries that respond in milliseconds — a market Cummins is targeting with its BESS platform, including what it calls its largest deployment to date.

Terms in This Story

BESS
Battery energy storage system — a battery installation that stores electricity and can charge or discharge very quickly to smooth out power fluctuations on a site or grid.
ride-through
The ability of a facility to stay connected and keep operating through brief voltage or frequency disturbances on the electricity system, then recover power within defined timeframes.
PSCAD
Power Systems Computer Aided Design — an industry-standard simulation software used to analyze fast electrical transients, power electronics and complex grid interactions.
hyperscaler
A very large cloud and computing operator that runs massive fleets of data centers.
Read Original: Cummins Inc.